Migrating historic (already finished) processes

Is there any way to migrate processes which have already terminated/finished in a BPMN process when upgrading the version (deploying a new process)
I have a requirement that needs me to restart the finished process sometimes and if the historic/finished processes dont carry over i wouldn’t be able to restart them

Hi Abhinav,

It is not possible to use the migration for already terminated/finished instances.
You need to perform two steps in your use case:

  • restart the finished process instances
  • and migrate to the newer version

Best regards,